This is an unremarkable anecdote. I've done this many, many times.
Nothing about this is special, yet most people will not do this on projects.
For us, this is the basic expectation from our team.
Story time:
On **Tuesday** of last week, I issued an open spec to the electrician for a **round** floor box that will be embedded in concrete.
Now, for any of you who are unfamiliar, an "open spec," in our world, means a specification that meets certain requirements.
The components don't **have** to be from a certain manufacturer, they simply have to match certain requirements. This usually means "find the closest available that meets all other requirements" like *availability.*
In the open spec, I noted a **very** well-known manufacturer that typically has readily available components.
The main reason I did this was because we have an imminent concrete pour. This means we need to get the embedded component immediately, so we don't delay the schedule.
On **Friday** the electrician sends an email saying:
"I didn't find what you asked for, but I found this *square* floor box. It is two weeks out."
Now, I'm not one to micromanage, and I hate doing other people's work for them, but delaying the schedule was a non-starter.
Preserving the schedule is my job. And while there are instances where I can't do anything about it, I am extremely aware of the instances where I can.
So, I do a web search for the manufacturer I had noted in the spec. The **very first** result is for a national supplier who has the part in stock one state over.
I call them to confirm the part is available, and I make friends with Amanda, who graciously offers to refund me the rush and 2nd day air shipping fees, and I place the order for the parts on the spot.
Yesterday, Monday, I get the floor boxes and we are good to go.
Some of you with experience will ask "why didn't you issue the spec sooner?"
The answer is, I did.
The electrician didn't get around to it until the concrete forms started going up, which is why I pivoted to a readily-available option. I was making his life easier without sacrificing what the project needed.
Two thoughts here:
1 - If you're a young person starting in construction or development, and you have the wherewithal and agency to do this, do it.
2 - I've grown not to expect this from anyone outside of our team, but I will often leave this open for people to step up. That has rarely been the case.
The bar is fairly low, and I'm aware this doesn't just apply to development and construction.
Owning your work looks like a few different things, one of them is showing up with agency when given the chance.
And if you're ever given the chance, you really should take it.