I don't think many people realize how much behind-the-meter data center capacity is likely to come online in the coming years.
Today's numbers look relatively small. 3.8 GW operating and 6.2 GW under construction, according to our tracker at Cleanview.
But the pipeline is much bigger. There's about 125 GW of planned BTM capacity.
People are right to be skeptical that all of this comes online. But there's about 82 GW in the pipeline that looks pretty legitimate and likely. These projects have equipment, named tenants, experience, and/or hyperscaler backing etc.
Depending on how you cut the data, 20-30% of planned data center capacity is expected to come from BTM capacity.
Some of that is from temporary turbines. But a ton of it is planned to operate for 10+ years. Amazon's GW Ranch is 7.65 GW of nameplate gas capacity and has no plans to interconnect.
There's been a group of people who have been skeptical of these projects from the start and have convinced their audiences and followers they'll never be built.
I don't pretend to be able to predict the future. But if you think BTM data centers will be inconsequential, you should update your priors and consider listening to a few new podcasts.