At 12:33 on 28 April 2025, mainland Spain’s grid fell from 25 gigawatts to zero.
That night our Head of Finance wrote to us from Spain: “its been crazy, no traffic lights, no phone signal, no power anywhere for 10hr”.
That grid is fragile, and it is full. In 2024, half the businesses that asked to plug into it were told no. So we are buying, and rebuilding it.
This summer we bought the first piece, a transformer centre in La Barona and the lines that run from it. Power comes in at 20,000 volts and leaves at the voltage in your socket. Within weeks it becomes the first piece of that grid we have rebuilt, starting with its switchgear. Our design for that switchgear alone runs to 108 pages. We’ll write the grid’s billing software too. In the UK we get that bill, and in La Barona we send it.
We’ll do the same to every grid we buy, then build generation and storage beside it, so it can carry far more. The usual answer to a full grid is to ask people to use less. Ours is abundance, because every data centre we connect makes power cheaper for the homes on the same cables.