$NBIS: Explaining DataOne Winding Down Temporary Generators
In Q3 earnings call, many investors did not understand what was meant by "DataOne decided to wind down the temporary generation faster than it was expected" (1). It's not Nebius or DataOne's fault nor was it permitting issues. Let me unpack it.
@SMASIMHO was right that Vineland is a 100MW class Fuel Cell site. I thought that it couldn't be the case because 100MW of BTM electric aggregation with voltage and frequency fluctuation smoothing would take longer to build. It turns out we were both right at the same time.
You see, Vineland did have 100MW+ of BTM mini-grid built by July for the temporary generators. When the BE Fuel Cells shipped onsite, they could be in operation within a one or two weeks, the power generation was never the bottleneck.
So you have two power sources both ~100MW each but only 100MW mini-grid to plug into, which one do you plug in? Obviously the BE Fuel Cells because they are more fuel efficient and cleaner for the environment. The unplugged generators? Well you just wind them down.
This entirely makes sense because in BE's earnings call, BE said that they were not the bottleneck. In fact, I'm pretty sure BE could have 300MW of BE Fuel Cells operating at Vineland by the end of Q3 2026, but 200MW would be not plugged into anything and BE would be billing for whatever is onsite.
A BTM site is a mini-grid that's behind the grid with all the power electronics to control out voltage and frequency fluctuations.
This is why NBIS stated "We now expect the ARR we guided to for December to arrive in February, even before New Jersey ramps up to full capacity" (2) and guided for Vineland to be fully 300MW online in H1 2026. What's taking so long is the BTM mini-grid.
DataOne is doing a fantastic job because to rebuild a 300MW BTM mini-grid from Bergen to BE with lead times actually takes 12-18 months or about the same time as the electrical distribution in datacenter. But DataOne has MV transformer production in house so the delay for Vineland is only 3-6 months delayed.
An astute read might ask, shouldn't have DataOne been preparing the BTM mini-grid for the Bergen Engines to be 300MW? As I explained previously, the BTM mini-grid for Bergen Engines is different than for BE Fuel Cells, so they have rebuild to the a different BTM architecture which is still faster than building from scratch.
@jiahanjimliu$NBIS: Vineland 8/5/26 Amended Site Plan Hearing
Credits to @ilzmcfly for local contact to provide me full public documents.
Documents
The Vineland City meeting agenda For DataOne can be found online: https://www.vinelandcity.org/Archive/Planning%20Board/Agendas/2026/Agenda%208-5-26%20%28Special%20Meeting%29.pdf
From this official Vineland agenda, you can confirm that the plan includes:
1. 4x ground mounted Bloom server areas at 52.2k sqft each for 208k sqft.
2. Three 2-story platforms for Bloom servers at 52k-55k sqft per floor for 319.8k sqft.
3. Two 3-story platforms for Bloom servers at 64.6k sqft per floor for 388k sqft.
This is a total of 915.8k sqft or 21 acres.
I will reference the full plans and permits which you can request from the city here: https://cityofvinelandnj.nextrequest.com/
Updated Plan
Now with concrete site plans and approvals we can do a full analysis of Vineland. The site level plan is provided in picture 1.
The Bloom servers, themselves, are a big win for $NBIS. The Bloom servers themselves will be installed on time and do not need the Air Quality Permits that the Bergen Engines were indefinitely waiting on (picture 3).
The risk delay for $NBIS is due to the large change in behind the meter (BTM) electric and natural gas distribution architecture.
1. The sheer difference in routing electrical and gas to 32 Bergen Engines vs 1010 bloom engines gridded over 21 acres.
2. Bergen Engines are a grid forming power source while bloom engines are grid following power source at different voltages so the BTM architecture changes. The electrical support infrastructure for Bloom servers will be MV switchgear, step-up transformers, AC power conversion equipment (picture 2).
I have put the 100+ pages of plan documentation into ChatGPT Pro (picture 4) to generate the following findings:
I am assuming $NBIS/DataOne has prepared, in advanced, the long lead time electrical equipment; otherwise Vineland would only be at full power in 2028.
A fast buildout of the BTM electrical and gas distribution for 1010 Bloom Servers over 21 acres will allow Vineland to come to full power in tranches throughout 2027.
Currently Vineland is powered by up to 125MW of temporary gensats (1). These temporary gensats can only operate without air permits for 12 months (2).
Bloom Server vs Bergen Engines
Bloom is responsible for installing, operating, and maintaining the Bloom servers but not the BTM electrical/gas distribution architecture. This is where the large difference between the two lie
Bergens Engines go:
Gas -> Bergens -> 13800V (13.8kV) -> MV AC Bus
Bloom Servers go:
Gas -> Bloom Servers -> 480V AC -> Step-up Transformers -> MV AC Bus
The DC to AC conversion is packaged within the Bloom servers and the responsibility of $BE and that outputs the 480V AC shown. The step up transformers, MV lines, and natural gas distribute pipes are the responsibility of $NBIS/DataOne.
If Datacenter is centered around power distribution to servers, then BTM architecture for Bloom servers is the aggregation - symmetrical but reversed. This requires PDS boards, LV feeders, protection relays, LV-MV transformers.
The most important thing to note here is that the 480V Bloom server output is LV while the Bergen Engines output is 13800V (13.8kV) which is already MV.
Bergens also are grid forming so UPS/BESS are only needed as backup. Bloom servers are grid following, so more UPS/BESS are needed as the microgrid VF stabilizer.
The gas distribution isn't as complex as the electrical architecture but the sheer scale is the difficulty. Distribution to 1010 Bloom servers spread over a 21 acre grid going up platforms while maintaining flow rate and pressure.
Bloom Server Platforms
Previously, I had noted that the Bloom Servers would take a large land mass but said that Vineland has enough land. Well, Vineland does have enough land but there's other infrastructure that needs space so DataOne is going to have to build enormous two and three story platforms to fit everything.
This will entail structural foundations, seismic/vibration protection, gas piping to multiple elevations, electrical routing, gas and fire detection, maintenance access and safety clearance. These structures in aggregate will be much more volume than the datacenter structure.
In-Depth Analysis of LV-MV Transformers
If not prepared ahead of time, these are the longest lead time items. Exactly sequence of voltage transformations is not specified but two possible architectures would be:
1. 65 LV-MV transformers stepping up 5MW blocks. 328MW nameplate would eventually become 250MW as cells age. This is the guaranteed 250MW.
2. 35-40 LV-MV transformers if larger 10 MVA collector transformers are used.
Accompanying this would be far more MV switchgear and MV breakers than the Bergen design.
The lead time for these items are typically 12-18 months but I assume $NBIS/DataOne has ordered well ahead of time.
Conclusion
Assuming long lead times items are taken care of, the construction of BTM architecture is a significant challenge. If a 300MW Datacenter is about distribution power to 1000 racks, a 300MW Bergen server BTM microgrid is about the aggergation of power from 1010 Bloom servers. Trade the liquid cooling piping for natural gas distribution piping.
When you move from 32 Bergen engines to 1010 Bloom servers, a 31x difference, you no longer have a simple power source but a "reverse datacenter" microgrid.
It took DataOne almost 18 months to build the datacenter, and now they have to 4 months to build the Bloom server microgrid. There is a very high probability risk that Vineland at 250MW+ is a 2027 event.
If $NBIS had started with Bloom fuel cells from the very beginning, Vineland would have most likely finished by the end of 2026. However, the tragedy is that $NBIS tried to save money on the power source and went with the much cheaper Bergen engines. The irony is that Arkady talks about cheap power, yet he's going to miss deadline on his 19.4B MSFT contract because he tried to save money on power.